Our Kitchen Makeover
Done by Kitchen Design Concepts
Starting January 24th 2005

Week1 Week2 Week3 Week4 Week5 Week6 Week7 Week8 Week10 Week11 Week12 Finish1  Finish2 FINAL

Before:

Living room side of the fireplace/wall

Kitchen side of the fireplace/wall

Day1

:

Day2:

Day3:


Support Beam goes up (walls are temporary)

Day4:


Temp walls come down

Day5:

Day6:


Entry hall walls go up.

Day 7:


Windows start getting framed and second door gets closed off.
Lighting goes is.

   